Company Status

Status

  • Security Clerance Received on: 16 OCT 2024
  • Local Acquisition Under Progress: DAT/Local Acquisition/2025/00000/4290 Dated: 16-06-2025
  • LOI Between TASPL And Global Coal & Mining Pvt. Ltd. Done. 
  • CAMO Contract Given To Thriveni Earthmovers Pvt. Ltd. a DGCA approved CAMO Subpart G Org. 
  • Appendix A, B & C Submitted on dated: 23 June 2025
  • OM submitted as per CAP 8100 – eGCA FSD/OPM/2025/2423 Dated: 25-05-2025

Post holders approval will be submitted on through eGCA for DFO, D-Training, CFS & SMS Manager.
FSM, SMS, FSDS & OPS Manual submitted through e-CGA.
TASPL- Security programme submitted, awaiting approval. CSO’s Training Completed.
MEL , AMP , TECH LOG , LOAD & TRIM , LOAP & ESEL under progress for approval.

SPL OPS - RVSM, ADSB & PBN : Separate application will be submitted through eGCA.
Night parking received on dated 20-06-2025.
Ground handling agreement signed between TASPL and BWFS.

NSOP Approval- Timelines

Comprehensive Overview of Aviation Compliance & Certification Progress

Phase – 1 (PAM) Conducted on 09-April-2025

Security clearance, Security programme application, Post Holders Nomination

Phase – 2 (FAM) Conducted on 04-July-25

Manual preparation, FAM application, FAM meeting

Phase – 3 (Scrutiny of Manuals)conducted on 01 Aug. 2025

Scrutiny of manuals, Responses to shortfalls, NOC for local acquisition, C of R application, Grounding of aircraft

Phase – 4 (Inspection & Demonstration)conducted on 21 Aug 2025

Tabletop exercise, Office inspection, Aircraft inspection, Demonstration flight

Phase – 5 (Certification for NSOP) conducted on 31 Aug 2025

Compilation of responses, Clearance, NSOP issuance